Water Level Basics
How Canals and Locks Work
Chapter 2 · Water Level Basics
Chapter 1 showed why a boat on still water is so easy to pull: there is almost no resistance. That only works if the water really is still. A canal is a long thin lake built on sloping ground, and water does two awkward things: it runs downhill, and it soaks into the ground. This chapter is about how builders cope with both, by keeping canals level and by making the bed hold water.
Water Finds Its Level
If you tilt a bath, the water rushes to the low end. A canal is the same: a stretch of still water has a flat surface, however the ground beneath it slopes. A stretch of canal held at one level is called a pound. Along its whole length the surface is level, and the depth is greater where the ground dips and smaller where it rises, so builders dig and bank up the bed to keep a steady depth for the boats.
A pound ends at a lock (the subject of How Canals and Locks Work 3) or at the end of the canal, where the next pound sits at a different height. So the real question for a builder is: how do I get from A to B at a set of fixed levels, with as few steps as possible?
Contour Canals: Going Round the Hill
The cheapest way to avoid steps is to follow a hillside at a constant height, a contour, and let the route wind to keep its level. Many early British canals were contour canals, and the Oxford Canal, for instance, is famous for its winding course (check). The price is distance. The sum below compares a straight route over a hill, which needs locks, with a longer contour route that does not. The speeds, lock lift and lock time are assumed.
The contour route is 7 km longer but a little quicker, because ten lock passages cost two and a half hours. It also needs no lock keepers and spends no water on lockage. But the straight line is shorter to dig and build, so neither is automatically right: the sum has to be done for each hill.
| Feature | Contour canal | Canal with locks |
|---|---|---|
| Route | long, winding | shorter, straighter |
| Height change | none, one level | stepped, pound by pound |
| Journey time | no lock delays | each lock adds minutes |
| Water supply | needs only to replace leaks | every passage also uses water |
| Staff | few | lock keepers or boaters to work locks |
| Weakness | a long bank on a hillside that can slip or leak | delays and water demand |
Keeping Water In
Even on perfectly level ground, a canal loses water downward and sideways through the bed and banks. Sand and gravel drain freely. Clay holds water well. If the route crosses porous ground, the builders must seal the channel. How much does it matter? The code below uses a 10 km pound and assumed seepage rates (the depth of water lost per day).
A percent or so a day looks small, but it is lost every day, without a boat in sight, and the shortfall must be fed in from a reservoir or stream (the topic of How Canals and Locks Work 4). Bare earth loses twenty times as much as good puddling. In a canal with a thin water supply, that difference decides whether boats can float all summer.
Puddled Clay
Puddling means working wet clay, usually mixed with sand or gravel, until it becomes a dense, tough, nearly watertight skin. Workers originally trampled it with their feet, and later machines helped (check). The best-known name is James Brindley, who is associated with puddled clay lining on the Bridgewater Canal (check). Typically the clay is laid in layers around the bed and banks, kept damp while it is worked, and kept covered or filled, because a dry clay lining cracks. Stone or brick lining, and later concrete, were used where clay was not enough or where a bank needed strengthening (check).
Challenges
A canal must gain 18 m of height. Option A goes straight over: 8 km long, with locks that each lift 3 m and take 20 minutes. Option B is a contour canal with no locks, 13 km long. Boats travel at 3 km/h. Find the time each way and say which is quicker; then name two other things you would weigh up before choosing.
📄 View solutionA pound is 4 km long, 8 m wide and 1.2 m deep. Assume seepage of 10 mm of depth per day if unlined, 2 mm per day if puddled. Find the volume lost per day each way, the days for the level to fall 0.15 m with no top-up, and how many 21 m x 2.1 m x 2.4 m lock chambers the daily leak would fill.
📄 View solutionShort answer. (a) What is a pound, and why must the water in one stay level? (b) Give two reasons a builder might choose a contour route. (c) Name two ways to keep water in a canal bed, and say what puddling solves that bare soil does not.
📄 View solutionSummary
- Pound: a level stretch of canal between locks
- Contour canal: follows a hillside at one height: longer, but no locks
- Leakage: a small percentage a day adds up, and must be replaced from a water supply
- Puddled clay: worked wet clay that cuts seepage many times over bare earth; it must stay damp
- Trade-off: distance against locks, digging against leaks